The new upper level is at the final stages of completion now with the electrician due back to fit the power points, switches and light fittings and the plumber will fit off the tapware in the bathrooms.  The walk-in-robe and built-in-robes are being fitted out today and the carpet will be layed late next week.

The timber floors and stairs have been polished with just the handrail to be done.

Once the new upper level addition is finished off late next week which includes a detailed complementry clean, the Clients can move in upstairs.  This then will free up the areas to be worked on downstairs where the existing family room, bedroom and study will be opened up to be one spacious living area.  The renovations downstairs also include a new kitchen which is being built by Erwin Interiors & Cabinetmakers.

The carpenters Tim and Luke are working on the linear boards to the external walls of the double garage and new front entry.  The garage roof was tiled today so by the time the office mouse returns late next week the front entry and garage will be close to finished.  This is such an exciting time for our Clients, by next weekend they will be able to move into the new second story extension!