This time next week the new upper level will have the carpet laid, the final electrical work done and the bathrooms ready. Then the cleaners will do a final clean ready for the clients to move in upstairs.
This week the plasterers are finishing off the internal work downstairs in the family room, dining and lounge / front entry.
Rob and Lachy will have the downstairs extension and renovation work just about finished so the painters will be able to start their work throughout the lower level.
The old driveway has been removed ready for the new concrete driveway to go in and the garage door opening has been measured for the tilter door manufacture.
So when the office mouse returns late next week the new driveway will be in, the upper level will be finished and downstairs almost ready to paint!