With a break in the weather Tim and Luke had Rob and Lachy’s help (the other “A” Team carpenter gang) to get the upper level wall frames and roof trusses up making the most of the fine day! Great team effort by all.

The Clients are able to see the floor plan layout and room sizes now which is such an exciting stage in the extension process where their design ideas become a reality.

In the third week Tim and Luke will be putting up the sarking and bracing sheets to the exterior walls, the scaffolding will go up for the fascia and gutters to go on and for the roof which will go on by the end of the week.  The office mouse will definitely visit the site again at the end of the week there will be so much to see!